Resurfacing work on the A217 St Dunstan’s Hill that was due to start today (Thursday 11 March) has needed to be postponed by one week. It will now commence on 18 March from 10am.
The timetable for the work has been reviewed to minimise the impact of the changes for residents. So the work on the Southbound carriageway (18 March – 25 March) will be completed before the work on the Northbound commences (26 March – 3 April).
TfL apologises for the delay, and assures us that they are working tirelessly to ensure this programme maintains this revised timetable.